Golden West Food Group Enterprise Installation
The Challenge
Golden West Food Group needed comprehensive infrastructure across multiple networked production facilities including structured cabling for office and warehouse operations, extensive security camera coverage, access control for food safety compliance, and facility-wide paging systems—all while maintaining continuous manufacturing operations.
Our Solution
Our team deployed a phased installation approach, working section-by-section to avoid production disruptions. We installed Cat6a cabling throughout offices and warehouses, fiber optic backbone between buildings, 260 IP cameras with centralized NVR system, 200+ door access control points, and an integrated paging system for emergency notifications and production communications.
Technologies Deployed
- Cat6a Structured Cabling
- Fiber Optic Backbone
- 4MP IP Camera System
- Access Control Integration
- Networked Paging System
- Centralized Management
Services Provided
- structured-cabling
- fiber-optic
- security-systems
- voice-telephony
The Results
Delivered a fully integrated infrastructure supporting operations, security, and communications. The IP camera system improved security and provides valuable footage for safety training. Access control system ensures food safety compliance with detailed entry logs. Facility-wide paging enables rapid emergency notifications and improved operational coordination.
The project coordination was excellent. Cable-Com worked around our production schedule and delivered a complex integrated system that has significantly improved our security posture and operational efficiency.
Project Details
Completion Date
June 2023
Project Duration
5 months
Team Size
10 technicians